Tag: nashi-poekty-en

April 2015

April 2015

  Afipsky refinery. In April 2015 on Afipsky oil refinery were  carried out works of the movement of the vacuum column K-601 (weight 256 tons, diameter 9360 mm, length 35775 mm) above the acting overpass of technological pipelines.

READ MORE +

May 2013

May 2013

Novocherkassk In May 2013 on Novocherkassk power plant were carried out works of lifting and installation of the generator stator weighing 320 tons to a height of 11 meters.  

READ MORE +

January-February 2013

January-February 2013

YEAR 2013 Nizhnevartovsk Difficult rigging operation of lifting HRSG drums to a height of 35 meters indoors  was performed by specialists of JSC «Titran" in January-February 2013 in Nizhnevartovsk. The task was complicated by the cramped conditions of work and absence of auxiliary cranes. The basic part of ...

READ MORE +

September 2012

September 2012

YEAR 2012 Nizhnevartovsk We have fulfilled the installation of a gas turbine General Electric weighing 290 tons and generator weighing 218 tons by the hydraulic rigging system SBL1100 capacity of 1100 tons. To install the turbine on the support it was lifted to a height of 6 meters and was moved above the ...

READ MORE +

December 2011 – February 2012

December 2011 – February 2012

The gas turbine power station of Novy Urengoy Gas-Chemical Complex. JSC "Titran" carried out works for transportation from the warehouse of temporary storage  to the installation site and the installation on foundations of two gas turbine generators (weight of 79 tons each), a steam turbine generator (weight of 78 ...

READ MORE +

2011

2011

Liski Unloading of heavy seats up to 150 tonnes from the barge to the pier carried out by rigging crane-independent method

READ MORE +

June 2010.

June 2010.

Introduced to the work Hydraulic Lifting system 500-ton lifting capacity lifting height up to 18 meters Installation on the Foundation 2 SIEMENS generators weighing 320 tons size 13000х4064х4159.  Kirishi

READ MORE +

May 2010.

May 2010.

Perm The transporting, lifting to 9 meters, moving and installation on the foundation of the steam turbine SIEMENS 110 tons and ABB generator 61 tons

READ MORE +

March 2010

March 2010

Lifting generator weighing 59 tonnes to 7.0 m. the Horizontal displacement at the Foundation was carried out the side of the generator.  Voronezh

READ MORE +