Tag: nashi-poekty-en

October 2018

October 2018

Volgodonsk From the end of 2017 to october 2018, our company performed dismantling, moving, erection, commissioning, as well as acceptance tests of the unique Schiess IFBW horizontal boring mill, at one of the largest production facilities in the nuclear industry. Our team of specialists managed to move the ...

READ MORE +

August 2018

August 2018

St. Petersburg Carrying out work at the Krylov State Research Center on loading 3 Hydroelectric motors, weighing 300 tons each, onto vehicles.

READ MORE +

July 2018

July 2018

St. Petersburg In July 2018, in the city on the Neva, repair work was carried consisting of the replacement of the return cylinders and the replacement of the master cylinder seal set on a German forging press with a force of 1600 Nm. The work was carried out in the condition of operating production and in a ...

READ MORE +

May 2018

May 2018

St. Petersburg In May 2018, "Titran" performed work on dismantling a set of autoclaves at the site of the LSR aerated concrete plant located on Oktyabrskaya Embankment in St. Petersburg, and on installing a set of autoclaves at the site of the new LSR plant located in Sertolovo, a suburb of St. Petersburg. The work ...

READ MORE +

March 2018

March 2018

Moscow Unloading of the stator of the TVV-350-2UZ turbine unit from a special railway platform and installing it on temporary bogies. Towing (moving) of the stator of the TVV-350-2UZ turbine unit on temporary trolleys to the working area of ​​special cranes.

READ MORE +

January 2017

January 2017

Saint-Petersburg, Southern Power plant No.22 On New Year's holidays specialists of our company in a short time carried out works of dismantling and re-installation of the stator of generator weighing 160 tons. The works were performed in conditions of acting engine hall, without dismantling of basic structures and ...

READ MORE +

August – September 2016

August – September 2016

Kamensk-Uralskii In the new shop of Kamensk-Uralsky Metallurgical Works have been carried out works for assembling of the rolling mill. The JSC "Titran" performed the installation  of housings of roughing stands. Two housings weighing 510 and 520 tons should have been canted in vertical position, moved onto ...

READ MORE +

May – July 2016

May – July 2016

Concern "Rosenergoatom" set for SC "Titran" difficult and responsible task - to replace the stator of generator 1 million kW power during the repair of the 3rd unit of Kalinin Nuclear Power Plant. Have been performed works for transportation, lifting, moving, loading and installation in the project position of two ...

READ MORE +

April 2016

April 2016

St. Petersburg. On the Baltic Shipyard were carried out lifting and installation of two tanks of metal-water protection on the largest nuclear-powered icebreaker "Arktika". Height of lifting is 18 meters, weight of each tank is 250 tons. .

READ MORE +